May 2023 progress update at Benobble Heights

May 2023 progress update at Benobble Heights

Our construction team have been making great progress at Benobble Heights over the last month, and we’re excited to bring you this progress update as of 16th May 2023

Stage 1A and 3

  • Civil works is complete
  • Rehabilitation works are complete
  • Electrical works will complete in next 1-2 weeks
  • Weeding of the landscape area has commenced with seeding and turf to be installed in next 1-2 weeks

Intersection

  • Civil works is complete
  • Weeding of the landscape area has commenced with seeding and turf to be installed in next 1-2 weeks
  • Electrical works are currently underway

Stage 1B & 2

  • Civil works are currently underway
  • Rehabilitation works have commenced and anticipated to complete soon
  • Electrical works are progressing well
Beaudesert-Nerang Road & Jesse Daniels Drive intersection construction well underway with bitumen just laid
Rehabilitation in Stage 1 of Benobble Heights
Stage 3 road construction complete with lighting & landscaping coming soon
Stage 2 road construction progressing well

We’re thrilled to see works progressing in our Scenic Rim community and will be sure to keep you up to date with all the latest progress as things unfold. Don’t forget to follow the Benobble Heights Facebook page for more updates.